NEWTON, Kan. — Construction work on Main Street’s ADA ramps between 5th and 11th Streets will begin next week ahead of a major road project this spring.
Pavement patching in the driving lanes north of Eighth Street will begin April 22. Traffic will be narrowed to one lane in each direction. Beginning May 6, after the Newton Car Show, APAC will begin milling the asphalt on Main from the BNSF Railway crossing to 11th Street, which will take several days.
Any additional needed patch work will then be completed, followed by asphalt overlay.
All phases are expected to be complete by the end of June, weather permitting.