Feb 27, 2023

Two bridges in Hutchinson to be repaired

Posted Feb 27, 2023 5:28 PM
The map shows the approximate project locations, marked in red. [PHOTO: Kansas Department of Transportation] 
The map shows the approximate project locations, marked in red. [PHOTO: Kansas Department of Transportation] 

HUTCHINSON, Kan. — The Kansas Department of Transportation (KDOT) announced on Feb. 27, two K-61 bridges in Hutchinson will be repaired beginning around March 13.

The KDOT project will repair the K-61 bridge 1.2 miles north of the U.S. 50/K-61 junction. It is the first bridge north of Avenue G over the railroad.

The project also will repair the K-61 bridge 1.7 miles north of the U.S. 50/K-61 junction. It is the first bridge north of Avenue A.

The project will patch the bridge decks and place an overlay on the decks. It also will replace the bridge approach slabs.

During the work, traffic will be reduced to one lane in each direction.

The work is expected to be completed around mid-July.

Wildcat Construction Co. Inc., of Wichita, is the primary contractor for the $1,765,950 project.