HUTCHINSON, Kan. — Construction activity at Evergy’s McNew Energy Center south of South Hutchinson is beginning to bring workers into Reno County, with opportunities ahead for local contractors, food providers and people interested in skilled trades.

Debra Teufel, president and CEO of the Hutchinson/Reno County Chamber of Commerce, said that general contractor Kiewit has moved about 15 employees into the community. The construction workforce could reach about 650 at its peak, with subcontractors also involved.
The 710-megawatt combined-cycle power plant will initially require extensive groundwork and underground infrastructure before more visible construction begins, Teufel said. Electricity generation is expected to begin around late 2029 or 2030.

Local businesses could participate in work ranging from electrical installation, concrete and paving to security and landscaping. Teufel said opportunities also extend to food trucks serving construction crews and catering businesses providing meals for project events.
Businesses interested in subcontracting can contact the chamber to connect with Kiewit.
Teufel also encouraged people interested in electrical apprenticeships to contact the local International Brotherhood of Electrical Workers. She said a project of this duration could allow workers to advance from apprentice to journeyman while gaining experience at one construction site.

Incoming employees are already renting apartments in Hutchinson. Teufel said the influx should generate additional spending at restaurants, fuel stations, retailers and other businesses, supporting local sales tax collections.
Road improvements are another major component of the development. McNew Road will need upgrades to accommodate heavy equipment and increased industrial traffic.
Teufel said Reno County expects to seek construction bids for the first mile later this year, with work on the next two miles planned for 2027.
The chamber’s work on the industrial corridor began several years before Evergy announced the plant in October 2024. Teufel said donations from Sharon Kimbell helped acquire land for industrial development, while grant funding has supported roadway engineering and right-of-way costs. A new industrial park sign recognizes Kimbell’s support.
Although Evergy will be exempt from property taxes for the plant’s first 10 years, Teufel said the company is arranging a payment-in-lieu-of-taxes agreement with Reno County.
She said those payments are expected to total about $19 million over 10 years, beginning when the plant enters service. A portion would help repay bonds used to finance roadway improvements.
Teufel said the project represents years of preparation and coordination, with construction now bringing the community closer to realizing its economic benefits.